top of page
Writer's picturePádraig McEvoy

Capdoo Extension of Clane Inner Relief Road

Clane-Maynooth Municipal District Meeting, Friday, 7 July 2023


Outline drawing of the extension of the Clane Inner Relief Road through Capdoo.

Councillor Pádraig McEvoy


Question


Can the council update the committee on the progress toward completing the extension of the inner relief road through Capdoo, Clane?


Agenda Report


The design of the Capdoo Inner Relief road in Clane has now been substantially agreed with Kildare County Council and a legal agreement will be signed off shortly between Kildare County Council and the Developer, after which construction works should start on site in Q3 2023. A Resident Engineer will be supervising the works on site. The estimated contract period is between 12 to 18 months.


Issued By: Mr. M McLoughlin, A/Senior Executive Officer, Transport, Mobility and Open Spaces.


Meeting Minutes

CM19/0723 [Link]


"The members considered the following question in the name of Councillor McEvoy


Can the council update the committee on the progress toward completing the extension of the inner relief road through Capdoo, Clane?


A report was received from the Transport, Mobility and Open Spaces Department informing the members that the design of the Capdoo Inner Relief road in Clane has now been substantially agreed with Kildare County Council and a legal agreement will be signed off shortly between Kildare County Council and the Developer, after which construction works should start on site in Q3 2023. A Resident Engineer will be supervising the works on site. The estimated contract period is between 12 to 18 months.


The report was noted."